Some significant disruption inbound from Monday on the outskirts of the town.
Calder Road and Westburn Road will be closed between Blantyre Farm Road to Hallside Road, Cambuslang from 7am on Monday 13th January to 5pm…..6 months later on 29th June as the new roundabout is constructed.
Traffic on Blantyre Farm Road is expected to be busier than usual during this lengthy duration.
Diversion route for vehicles under 4.6m – Blantyre Farm Road, A724 Glasgow Road, Hamilton Road, Westburn Road and vice versa. Diversion route for vehicles over 4.6m – Blantyre Farm Road, A724 Glasgow Road, Hamilton Road, Mill Road, Old Mill Road, Westburn Road and vice versa.
Planning and preparation works have previously been reported here on Telegraph.