Blantyre Braes Wastewater Infrastructure to receive significant upgrade

Scottish Water have committed to a multi million pound upgrade investment for their existing wastewater infrastructure at the Blantyre Braes.

The works to existing unpopulated land at Craighead Woods at the end of John Street, north of the Railway is due to commence shortly with advance access works to the area now underway.

The aim is to reduce sewage-related litter and improve the River Clyde environment and nearby Clyde Walkway , making things cleaner for residents, walkers and wildlife, as part of an ongoing programming of Improving Urban Waters.

Scottish Water proposes a new underground sewer overflow chamber with a powered screen to capture debris before overflow water reaches the existing outfall towards the River Clyde. Works are out of sight, below ground with these environmental improvements targeted by December 2027.

The intended benefit is less visible sewage litter, a cleaner local water environment and a more pleasant area for everyone enjoying the woodland and nearby paths.

Scottish Water and South Lanarkshire Council held several meetings during 2026 to shape the proposals. A planning application covers ground-level changes, an access gate and tree removal, while Scottish Water states that the underground infrastructure falls under permitted development rights.

As Craighead Woods is part of a Local Nature Reserve, environmental safeguards are particularly important. Further ecological surveys, tree assessments and a landscaping and biodiversity plan with replanting proposals are promised to help manage the impact.

Access to the works is via a haul road from the Whistleberry side with construction taking place primarily over the railway at the end of John Street, some distance away from any homes. Some trees would need to be removed, and temporary path diversions or closures may be necessary during construction. However, upon completion of the project next year, landscaping works would be undertaken with intention of removing any sign of construction activities. Scottish Water is working with council officers to minimise disruption, with temporary facilities removed and affected land reinstated as far as reasonably practicable afterwards.

The aim is a lasting improvement to this valued part of Low Blantyre — protecting the water environment while making the woodland and riverside welcoming, cleaner and safer for the community.

#Blantyre #CraigheadWoods #RiverClyde #LocalEnvironment #ScottishWater

This and further information about this interesting project can be found in the public domain online. Please see South Lanarkshire Planning Ref. No: P/26/1257